1st Project with Total Energy
MARCH 2022
Mobilization of the GGS team with a 2’’1052 HP Manifold on AGMC for the unlocking of well 43.
The GGS specialist team was promptly mobilized to address critical malfunctions in well 43's control elements. To remedy this situation, we deployed a 2’’1052 HP Manifold on AGMC, a highly effective solution specifically tailored to this type of intervention. This swift and efficient mobilization successfully cleared the well, paving the way for urgent and precise repairs to restore its optimal functionality.


April 2022
Mobilization of the second pumping team for phase AGM43 on a boat.
The second pumping team of GGS was precisely mobilized for phase AGM43, also known as AGMC. This mobilization involved the careful deployment of necessary equipment aboard a specially adapted boat. Through meticulous planning and efficient logistics, our team was able to set up the required resources for this critical phase of the project. This step is essential to ensure the ongoing success of our operations and maintain high standards of quality throughout the process.


May 2022
Mobilization of the third team for the production of brine at Total Energy's living base.
A third team from GGS was mobilized at Total Energy's living base to undertake the production of brine, an essential solution used for the control of well AGM43. This critical step requires technical expertise and specialized equipment, all carefully prepared and led by our experienced team. With our commitment to operational excellence and our ability to quickly respond to the changing needs of the project, we ensure efficient and reliable production of brine, thus contributing to the overall success of the operation.

2ème projet avec Total Energie : TCN 02, Rigless
August 3, 2022
TEST YARD AND PUMPING EQUIPMENT MOBILIZATION
Gabon General Services completed this pumping system integration project. Rigorous testing in a controlled environment optimized performance. Equipment mobilization was meticulously planned to meet deadlines and minimize disruptions. Commissioning followed standard protocols and procedures.


NovembEr 7, 2022
TEST YARD AND MOBILIZATION OF SLICKLINE EQUIPMENT
The completion of the Test Yard project and the mobilization of the Slickline equipment were pivotal milestones in our journey. Our team showcased its expertise by efficiently managing the testing process and ensuring the successful mobilization of the Slickline equipment on-site. Through meticulous planning, seamless coordination, and unwavering commitment to quality, we ensured the smooth execution of each phase of the project. This achievement demonstrates our ability to tackle complex challenges and deliver innovative solutions to meet the specific needs of our clients in the oilfield services sector.


3rd PROJECT WITH TOTAL ENERGY: TCNE 03 WITH THE NEW UNIT INIVA
January 2023
VISIT OF THE PULLING UNIT INIVA